Contract Payment Process

The Capital Improvement Project payment process for construction contracts involves several City Divisions and includes:  the Contractor, the Construction Inspector, the Contract Payment Specialist and the City Engineer.  Payments are generated on a monthly basis until the project is completed.

Construction Contract Payment Process

  • Notice to Proceed (NTP) date starts the payment process
  • Contractor works on project
  • Each month, the Engineers Estimate of Work Completed is sent to Construction Inspector
  • Construction Inspector and Contractor verify and agree to field quantities
  • Engineers Estimate of Work Completed with field quantities is sent to Contract Payment Specialist
  • Calculated Engineers Estimate of Work Completed is faxed to Contractor for approval
  • Engineers Estimate of Work Completed is sent to Accounting for processing and check printing
  • Check is issued and mailed to Contractor or called for pick up arrangements

Payment processing additional information